Industries

We act on domestic and international construction, mining, power and infrastructure disputes involving rigorous contractual, quantum and delay analysis.

Meet the Principal Expert

Albert Merolla explains how Build Conex approaches delay and quantum disputes with forensic rigour, clear contractual analysis, and proportionate reporting.

Quantum & Delay Services

Albert Merolla JD, MCIBSE, MRICS, MAIPM, is a multi-qualified Chartered Engineer, Chartered Quantity Surveyor, and Registered Adjudicator with over 30 years of experience providing independent expert reports, evidence, and testimony in delay and quantum disputes.

When your case depends on clear, defensible valuation evidence, you need an expert who understands both the technical and financial realities of construction disputes. Our analysis addresses causation, concurrency and criticality, rather than retrospective narratives.

Quantum Analysis

Valuation of claims using the contractual mechanisms and project evidence, not global allowances or reconstructed narratives.

Delay Analysis

Assessment structured to address causation, concurrency and criticality, rather than retrospective narratives.

Claim Preparation

Testing, refining and reconstructing claims so they can withstand scrutiny in adjudication, arbitration and court.

Expert Reports

Non-partisan reports that assist in clarifying the issues genuinely in dispute, facilitating early commercial resolution.

Quantum & Delay Experts

Our Process

1

Instruction and Briefing

Understanding the dispute, the contract, and the records.

2

Preliminary Review

Rapid assessment of entitlement strength and evidentiary gaps.

3

Forensic Analysis

Detailed examination of the programme and records.

4

Quantum Valuation

Valuation by reference to the contract and records.

5

Draft Report

Structured facts, analysis, and conclusions.

6

Final Report & Testimony

Independent expert reports for adjudication, arbitration and litigation.

Report Structure

1

Executive Summary

2

Background

3

Events Leading to the Dispute

4

The Dispute

5

Contractual Framework

6

Causation & Delay Analysis

7

Valuation and Quantum

8

Opinion

Expert Report Approach

Although I hold formal legal qualifications, I do not act as a lawyer in these engagements. I am retained solely as an independent expert. This separation is deliberate — expert evidence must remain independent of advocacy.

My function is to assist the court or tribunal by analysing the evidence and the contract, then stating what is supported — and what is not. Legal conclusions are left to counsel.

The report integrates causation, delay and valuation within a single framework. Each section builds on the previous. The analytical sequence is: Contractual Framework, Causation, Delay Analysis, Quantum, and Opinion. This prevents conclusions from floating without foundation.

Reports & Assessments

About Us

Where claims commonly fail and how we address these deficiencies

Our clients often seek an early, proportionate assessment of entitlement and value to minimise further commercial exposure. Our non-partisan reports assist in clarifying the issues genuinely in dispute, so that both sides have a clear understanding of entitlement, valuation and risk. That clarity facilitates early commercial resolution.

This is because construction disputes often turn less on the underlying work than on how entitlement is evidenced, priced, and presented. Common points of attack include alleged failures to notify, reliance on time bars, fragmented delay analysis, and quantum claims unsupported by contemporaneous records. Our work is directed to addressing those issues from the outset.

About Us

Our analysis is structured to address causation, concurrency and criticality, rather than retrospective narratives. Quantum is assessed by reference to the contract mechanisms and the project records, not global or impressionistic allowances. Where notice provisions and time bars are raised, the analysis distinguishes between strict contractual compliance, waiver, knowledge, prejudice and the actual operation of the clause in context.

Certifications

Industry Memberships

RICS
CIBSE
Chartered Engineer
CIArb
AIPM
ICCP

Discuss your dispute or claim to assess entitlement, evidentiary strength and recovery strategy.

Get in touch